Canyon Lake Phosphorus Management Program

Updates on The Alum Treatment Project for Canyon Lake from Aquatechnex

Day 1 Summary

Leave a comment

Aquatechnex completed the Eastern portion of the East Arm today.  The alum treatment staged from the East Ramp and two 4,300 gallon tank trucks were dispatched and unloaded to application vessels and applied.

Tomorrow operations will focus on completing the East Arm.  Three trucks will be delivering Alum to a site on the south shore half way down the East Arm.  We will be starting in Finger No. 6 on the treatment map and moving to the west toward the main lake.  Again, two vessels will be working on the water.

Tomorrow’s twitter feed will start about 8 am.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s